Genel Energy's Sarta-2 well enters production
Genel Energy
83.50p
17:10 25/04/24
-0.60%
-0.50p
Genel Energy said on Monday that the Sarta-2 well, in which it has a 30% working interest, has entered production, with gross field production now in excess of 10,000 barrels of oil per day.
Oil & Gas Producers
9,649.24
17:09 25/04/24
-0.08%
-8.14
The oil company said it expects this figure to increase from the existing two producing wells, "as optimisation of facilities configuration continues post production start-up".
The high-impact 2021 appraisal drilling campaign is on track to begin at the start of the second quarter, Genel said, with the Sarta-5 and Sarta-6 wells set to be drilled back to back.