Angus Energy outlines work programme for Brockham

By

Sharecast News | 03 Apr, 2019

14:15 29/04/24

  • 0.38
  • 1.96%0.01
  • Max: 0.40
  • Min: 0.35
  • Volume: 2,357,224
  • MM 200 : n/a

Angus Energy announced a timetable to its proposed operations at Brockham on Wednesday, with works set to begin on or around 12 April.

The AIM-traded firm said following the start of works, rig acceptance and mobilisation should take three days, with the isolation of water, reperforation and recompletion taking up 19 days of work.

Rig demobilisation would then take place over six days, followed by a 14-day lead time for the arrival of the well test kit.

The installation, testing and commissioning of equipment would take place over 10 days, with the flow test and production results occurring over 11 to 16 days.

“We are pleased to be able to evidence that our commitment to comprehensive communications with shareholders is being delivered in a timely fashion,” said Angus Energy interim managing director George Lucan.

“We look forward with excitement to completion of these works.”