Samarco Update

By

Regulatory News | 21 Nov, 2017

Updated : 07:01

RNS Number : 0397X
BHP Billiton PLC
20 November 2017
 

 

NEWS RELEASE

 

Release Time

IMMEDIATE

Date

21 November 2017

Location

Melbourne

Release Number

35/17



 

SAMARCO UPDATE

 

Samarco Mineração S.A. (Samarco) and its shareholders, Vale S.A. (Vale) and BHP Billiton Brasil Ltda (BHP Brasil), have entered into an agreement (Amendment Agreement) with the Federal Prosecutors' Office in Brazil (Federal Prosecutors) and the Minas Gerais State Prosecutors Office (State Prosecutors). The Amendment Agreement amends the preliminary agreement entered into on 18 January 2017 in relation to the Samarco dam failure (Preliminary Agreement).

 

The Preliminary Agreement outlines the process and timeline for negotiation of a settlement of the BRL 155 billion (approximately US$47.6 billion) and BRL 20 billion Public Civil Claims (approximately US$6.1 billion) relating to the dam failure (Public Civil Claims). It also provides for the appointment of various experts to advise the Federal Prosecutors.

 

The Preliminary Agreement suspends a BRL 1.2 billion (approximately US$0.4 billion) injunction order under the BRL 20 billion Public Civil Claim and requests suspension of that claim, with a decision pending. The BRL 155 billion Public Civil Claim is also suspended, including the BRL 7.7 billion (approximately US$2.4 billion) injunction requested by the Federal Prosecutors. Under the Preliminary Agreement, Samarco, Vale and BHP Brasil have provided interim security to the Court.

 

The Amendment Agreement provides for the State Prosecutors to become a party to the Preliminary Agreement. It also provides for additional community consultation. The Amendment Agreement includes a process for seeking to agree new socioeconomic experts to advise the Federal Prosecutors, and contains some further requirements as to how those experts would conduct their work.

The Amendment Agreement is subject to ratification by the 12th Federal Court.

 

Samarco, Vale, BHP Brasil and the Federal Prosecutors have also jointly requested, and the 12th Federal Court has approved, an additional 150 days, ending on 20 April 2018, for the parties to continue negotiations for the settlement of the Public Civil Claims.

 

During the 150 day extension period, the interim security arrangements provided to the 12th Federal Court and the current suspension of legal proceedings and injunctions under the Preliminary Agreement will remain in place.

 

Further information on BHP can be found at: bhp.com

 

Media Relations

 

Email: media.relations@bhpbilliton.com


Investor Relations

 

Email: investor.relations@bhpbilliton.com




Australia and Asia

 

Ben Pratt

Tel: +61 3 9609 3672  Mobile: +61 419 968 734

 

United Kingdom and South Africa

 

Neil Burrows

Tel: +44 20 7802 7484  Mobile: +44 7786 661 683

 

North America

 

Judy Dane

Tel: +1 713 961 8283 Mobile: +1 713 299 5342


Australia and Asia

 

Tara Dines

Tel: +61 3 9609 2222  Mobile: +61 499 249 005

 

United Kingdom and South Africa

 

Rob Clifford

Tel: +44 20 7802 4131  Mobile: +44 7788 308 844

 

Americas

 

James Wear

Tel: +1 713 993 3737  Mobile: +1 347 882 3011

 

 



BHP Billiton Limited ABN 49 004 028 077

LEI WZE1WSENV6JSZFK0JC28

Registered in Australia

Registered Office: Level 18, 171 Collins Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015


BHP Billiton Plc Registration number 3196209

LEI 549300C116EOWV835768

Registered in England and Wales

Registered Office: Nova South, 160 Victoria Street

London SW1E 5LB United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111




Members of the BHP Group which is headquartered in Australia

Follow us on social media

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
AGRBMBTTMBITTTR

Last news